IBM 000-155 Training Material Question 7
An System x customer has two BladeCenter chassis in a rack with glass doors. After recently relocating them, the blowers in both BladeCenters increase to full speed, and then one fails. Apart from replacing the broken blower, which additional action is required for a long term fix?
A. Add top of rack fans
B. Change to perforated doors
C. Add Rear Door Heat eXchanger
D. Increase circulation from the data center raised floor
Answer: B
An System x customer has two BladeCenter chassis in a rack with glass doors. After recently relocating them, the blowers in both BladeCenters increase to full speed, and then one fails. Apart from replacing the broken blower, which additional action is required for a long term fix?
A. Add top of rack fans
B. Change to perforated doors
C. Add Rear Door Heat eXchanger
D. Increase circulation from the data center raised floor
Answer: B